Home › Electrical Engineering Forum › General Discussion › Selective Coordination Tools and Spreadsheets (1)
- This topic has 0 replies, 1 voice, and was last updated 12 years, 11 months ago by elec master.
Viewing 1 post (of 1 total)
-
AuthorPosts
-
2012/01/18 at 6:17 pm #10766elec masterParticipantthe study of selectivity Coordination will be based on the following main points:Part One: What is selective coordination?Part Two: NEC code and Selective CoordinationPart Three: Method of performing a selectivity coordination study:First: By using Selective Coordination Time – Current Curvessecond: By using Selective Coordination Charts/Tables.Third: By using Siemens calculators / spreadsheets.Part One: What is selective coordination?Selective coordination is a design requirement where only the overcurrent device immediately upstream from the fault will operate, minimizing the outage caused by the fault.In the diagram above, only device C would open under the fault. For selective coordination, the system would be designed so that for a fault of any magnitude (up to the available fault current at device C) device C is guaranteed to clear the fault with neither B nor A opening.Part Two: NEC code and Selective Coordination:First: Before NEC 2005 Code:Prior to 2005, Selective coordination was only required for some Elevator applications by article 620.62 Selective Coordination:Where more than one driving machine disconnecting means is supplied by a single feeder, the overcurrent protective devices in each disconnecting means shall be selectively coordinated with any other supply side overcurrent protective devices.Until the 2005 NEC, a properly coordinated system was generally regarded as ensuring the timely operation of overcurrent devices to assure safety and protection of equipment (using damage curves) while minimizing nuisance trips. Designers have tried to minimize nuisance trips as much as possible by ensuring that there was no overlap in coverage in the thermal region of the time-current curves, and by adjusting the instantaneous range for as little overlap as possible. However, some overlap almost always existed and was accepted.Second: in NEC 2005 & 2008 Codes:2005 NEC Article 100“Coordination (Selective)” definition: “Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the choice of overcurrent protective devices and their ratings or settings.”New requirements were added in the 2005 and 2008 National Electrical Code as follows:Article 700.27 – Emergency Systems:Emergency system(s) overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices.Article 701.18 – Legally Required Standby Systems:overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices.2008 NEC – Article 708.54 – Critical Operations Power Systems (COPS)Citical operations power systems overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices.2008 NEC – Article 517.26 – Health Care FacilitiesThis article requires compliance with Article 700 for emergency systems, unless amended by the requirements in Article 517.Article 700.27 in the 2008 NECa clarification on the scope of the required coordination– “This coordination must be carried through each level of distribution that supplies power to the emergency system.”Third: NEC 2011 Code:In NEC 2011, some changes were done for the selectivity coordination as follows:700.27 Coordination.Emergency system(s) overcurrent devices shall be selectively coordinated with all supply side overcurrent protective devices.Exception: Selective coordination shall not be required between two overcurrent devices located in series if no loads are connected in parallel with the downstream device.701.27 Coordination.Legally required standby system(s) overcurrent devices shall be selectively coordinated with all supply-side overcurrent protective devices. Exception: Selective coordination shall not be required between two overcurrent devices located in series if no loads are connected in parallel with the downstream device.Paragraphs 700.27 and 701.18 modified the exceptions to address some questions about the required selective coordination. These exceptions don’t alter the impact of requiring selective coordination, but give technical assistance to the design engineer.517.17(C) Selectivity.Ground-fault protection for operation of the service and feeder disconnecting means shall be fully selective such that the feeder device, but not the service device, shall open on ground faults on the load side of the feeder device. Separation of ground-fault protection time-current characteristics shall conform to manufacturer’s recommendations and shall consider all required tolerances and disconnect operating time to achieve 100 percent selectivity.Paragraph 517.17(C) removed the requirement for six-cycle separation between the first and second level of ground fault protection. Instead, the new code allows manufacturer’s recommendations to be used to insure 100% selective coordination.Part Three: How to perform a selectivity coordination study?to read more, please follow the below link:
-
AuthorPosts
Viewing 1 post (of 1 total)
- You must be logged in to reply to this topic.