Re: electrical load schedule

#12233
admin
Keymaster

      First of all collect all the data from mechanical  and other process engineers regarding the type of equipments including static and rotating machines : obtain preliminary information about their perfomance and duties

  1. Determine the continuous running equipments, critical loads,
  2. determinine the intermittent loads
  3. determine the inductive , resistive loads,capacitive loads,
  4.  Fix the diversity factor
  5.  find out the maximum demand after determining the connected load
  6.  arrive at the peak demand
  7.  Make a tabulated schedule